The new design decouples the bathrooms and concessions into smaller buildings elevated about 5 feet to meet the 100-year floodplain.

Pittsfield Commission Sees Plans for $15M Rebuild of Wahconah Park

By Brittany PolitoiBerkshires Staff
Print Story | Email Story
On Tuesday, the Parks Commission saw plans for a $15 million rebuild of the historic-but-condemned grandstand.

PITTSFIELD, Mass. — On Tuesday, the Parks Commission saw plans for a $15 million rebuild of the historic-but-condemned grandstand. 

The project team hopes to begin construction in July, after the original 1919 structure is demolished. 

The new, half-cost design for Wahconah Park places the bathrooms and concessions in elevated, standalone buildings beside the grandstand. 

"We think this is a fair redesign for a very complicated site and a reduced budget in an environment of escalating building costs," Parks, Open Space, and Natural Resources Manager James McGrath said. 

The new design decouples the bathrooms and concessions into smaller buildings elevated about five feet to meet the 100-year floodplain.  An accessible ramp and porch would lead to the structures, and the grandstand would have a slightly narrower footprint. 

If begun this summer, construction would be complete in the spring of 2027. 

This grandstand is estimated to accommodate 1,100 people with benches and fixed seats, as well as an additional 700 in bleachers on either side.  Shaving down the capacity saved costs in plumbing, as the number of bathrooms is directly tied to the number of fixed seats. 

It was noted that continuing the well-received beer garden is a priority. 

"All in," including demolition and planning costs, the price tag is estimated at $17.5 million. Costs are reportedly tracking lower, and another estimate will be done.

The city has been allocated a total of $5 million in capital and federal dollars for the project, and McGrath reported that Mayor Peter Marchetti is comfortable with a $15 million capital authorization, pending community conversation and City Council approval. 

"What you're looking at is a very reduced scope of a project. The building has been very reduced, but the challenges with the floodplain still exist and are still very real," McGrath said. 


The scaled-down grandstand design does not include locker rooms or office space.  It was suggested that the Pittsfield Suns could bring in temporary structures for those uses, but there would have to be utility hookups on-site.  

It does clean up the parking lot and mitigate flooding, though floods will always occur to some degree because of the park's location. 

"I think the priority here is to get something up and running so that we can actually play ball there. And is it going to be what everybody envisioned right from the get-go? Sounds like it won't be, but if you get people out there playing, we can go and be fans of spectator stuff," Commissioner Simon Muil said. 

"That puts us way ahead of where we were this past summer." 

In December, the commission accepted a negotiating rights agreement between the city and the longtime summer collegiate baseball team, the Pittsfield Suns. It solidifies that the two will work together when the historic ballpark is renovated. 

McGrath reported that the Suns have expressed the desire to remain in Pittsfield. 

"I think the Suns are understanding of the city's need to scale the project, and I think the Suns are committed to working with the good, modern facility that we present at Wahconah Park," he said. 

"…The Suns do their best work on the field, and if we can provide a site experience in a secure location, a safe location, I think that's gonna be best for everyone." 

The commission also saw an update on the upcoming temporary ice skating rink that will be situated in front of the ballpark.  It is expected to be installed next week, and remain for six or seven weeks as an open skating rink. 

In the future, the city will look to add programming and skate rentals to the rink. 


Tags: Wahconah Park,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield Council OKs Underground Fiber Network

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — More underground fiber internet cables will be installed in Pittsfield. 

On Tuesday, the City Council approved Gateway Fiber's request to install an underground fiber network infrastructure within the city's right-of-way.  

The company was given the go-ahead for an aerial network last year alongside Archtop Fiber, marking the beginning of construction with a ribbon-cutting at the Colonial Theatre. Gateway Fiber will offer subscription plans ranging from $65 to $150 per month, depending on speed. 

Wards 3 and 4 will see the most work in the first phase, according to an underground fiber deployment plan.  Fourteen streets in Ward 4 will see underground fiber deployment; 13 streets in Ward 3.  

Ward 4 Councilor James Conant voted in opposition for personal reasons, as he signed up for Gateway Fiber briefly last year and said he had poor service and poor communication from the company. 

Some councilors and community members appreciated bringing competition to Spectrum internet services. Ward 5 Councilor Patrick Kavey pointed out that it costs about $90 per month for 500 megabytes per second with Spectrum, and that all three fiber services that have come to Pittsfield are cheaper. 

Operations Manager Jennifer Sharick explained that they were seeking approval for underground fiber deployment as part of the next phase in Pittsfield. The city was found to be a "very" viable community for underground fiber. 

Gateway Fiber, she said, originally served a community of 250 residents outside of St. Louis, Mo. 

"Following the pandemic, we saw the need, and what people need for fiber and reliable internet service to bring residents and businesses the opportunity for connectivity," Sharick said. 

View Full Story

More Pittsfield Stories