PITTSFIELD, Mass. Be advised that the following street improvements are scheduled from October 27-31:
Contracted Road Work:
10/27: Loam and seed Allengate Avenue, Taconic Park Drive and Tamie Way
10/28: Finish paving Taconic Park Drive, Tamie Way and Vista Street
10/29 & 10/30: Finish paving Allengate Avenue and Michael Drive
West Street project update
The construction of new sidewalks and curbing work continues. The traffic signal installation prep work also continues. During this work, lane closures at various sections are expected. We encourage drivers to seek alternate routes if possible.
Sidewalk Repairs:
Wendell Avenue between Broad Street and Colt Road
Bartlett Avenue between East Housatonic Street and Colt Road
During this work, the sidewalks above will be closed for pedestrian use. Pedestrians are asked to use the sidewalks on the alternate side of the street while construction is underway. This work will take several weeks to complete and the weather may have an impact on the schedule.
Additional utility underground work, in the right of way, will occur on the following streets:
King Street
Valentine Road (between West Street and Taconic High School)
Holmes Road
Franklin Street, West Housatonic Street (Cadwell Road to Britton Street), Gale Avenue
Dewey Avenue
Use caution when traveling on these roads. Drivers should seek alternate routes to avoid traffic delays. This schedule is subject to change based upon weather conditions.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Pittsfield Cleans Downtown Litter, Works on Outreach Program
By Brittany PolitoiBerkshires Staff
PITTSFIELD, Mass. — As the city develops a peer support outreach program, workers are clearing the downtown of potentially hazardous litter from the wintertime.
Over the past three weeks, the Health Department has sent out inspectors to assess sanitary conditions in the downtown, beginning on North Street, moving to First Street, and to the McKay Street parking garage.
"We've identified a lot of needles, and mostly needle caps and then small drug paraphernalia, and while we're identifying them, we're noting where we're finding them, and we're also picking them up and disposing of them properly," Director of Public Health Andy Cambi said.
"… We have not found any human waste sanitation issues currently, again, not to say that there isn't any, but I think it also speaks to the fact that we do have a new facility that's open, that's being run, The First, which does offer bathroom facilities, laundry facilities."
On Monday, he updated the Public Health and Safety subcommittee on the progress of the upcoming peer support outreach program and cleanup efforts in the area it will serve.
The First housing resource center opened in February in the basement of the Zion Lutheran Church with bathrooms, lounge spaces, lockers, and more. In its early days, it averaged about 50 visitors daily; on Sundays, an average of 70 visitors.
Cambi said he is in constant communication with ServiceNet, which is operating The First.
"It has been used heavily, so I think that speaks to the relief of issues that we're seeing in the downtown area in regards to those sanitation issues," he added.
"It's a great resource that's available that is being constantly used, so again, what it was intended for."
When the department comes across human waste, they will connect with Department of Public Works staff to have it cleaned and sanitized. Workers can make a clear distinction between pet and human waste, Cambi reported.
A statewide needs assessment prepared by the the Executive Office of Housing and Livable Communities (EOHLC) for the state's new Comprehensive Housing Plan had a stark analysis of the current status of housing throughout Massachusetts.
click for more
The building inspector's ticket book is running thin as the town starts to issue daily fines to Berkshire Concrete for its failure to submit a revised remediation plan for the unauthorized dig site. click for more
The Berkshire Regional Transit Authority is still working on maintaining its run schedules after dropping the route realignment proposal. click for more