image description
The wooden roof trusses recently installed on the new fire station toppled over sometime late Sunday.

Wind Damage Likely Will Not Delay Williamstown Fire Station Project

By Stephen DravisiBerkshires Staff
Print Story | Email Story

The trusses will be evaluated for repair and reuse but that work is not expected to affect the timeline or cost.  
WILLIAMSTOWN, Mass. — Recent wind damage at the new fire station's construction site will not cost the taxpayers any money and likely will not impact the project's timeline.
 
On Thursday morning, the district's construction consultant said the project's construction manager has a plan to resequence the schedule to make up for the time it needs to reconstruct wooden trusses knocked down by the wind over the weekend.
 
Bruce Decoteau, a retired senior project manager from Williams College, has been advising the Prudential Committee, which oversees the fire district, since the outset of the $22.5 million building project.
 
Decoteau said there are no cameras on site that recorded the damage, but the best guess from construction manager Consigli Construction is that the damage occurred at some time on Sunday evening.
 
According to the National Weather Service, the average wind speed in Bennington, Vt., the closest data point, was 15.1 mph with the highest recorded gust at 46 mph as of 4:43 Sunday afternoon.
 
"I got a photo early Monday morning advising me they had blown over," Decoteau said on Thursday.
 
Decoteau said the damage should have minimal or no impact on the project timeline, which currently has the Fire Department moving into the Main Street station at the end of the calendar year.
 
"What they'll do is pour the second-floor deck prior to installing the rest of the trusses," Decoteau said. "[Consigli] had it sequenced the other way around. This will allow them to keep the trades working and recover most of the time.
 
"You can't have people working underneath the trusses [pouring concrete] while you're setting them."
 
Decoteau said the town's building inspector told the contractor to have a structural engineer check out the steel structure below the trusses to make sure the collapse did not impact any of the metalwork, and the engineer confirmed that there was no effect.
 
"Everything is fine to go, and he sent a letter to Ryan [Contenta] stating accordingly," Decoteau said. "That allows us to get the crane on site and move the trusses to the ground."
 
The wooden trusses will be evaluated to see how much can be repaired and reused and how much needs to be replaced. Decoteau said based on observations from the ground, most of the wood should be usable.
 
As for the cost of repairs from the storm, that expense will be borne by the subcontractor who installed the trusses, Decoteau said.
 
"There will be no financial impact to the Williamstown Fire District or the Williamstown taxpayers," he said.

Tags: fire station,   wind,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Williamstown's Cost Rising for Emergency Bank Restoration

By Stephen DravisiBerkshires Staff
WILLIAMSTOWN, Mass. — The cost to stabilize the bank of the Hoosic River near a town landfill continues to rise, and the town is still waiting on the commonwealth's blessing to get to work.
 
Department of Public Works Director Craig Clough was before the Finance Committee on Wednesday to share that, unlike the town hoped, the emergency stabilization work will require bringing in a contractor — and that is before a multimillion dollar project to provide a long-term solution for the site near Williams College's Cole Field.
 
"I literally got the plans last Friday, and it's not something we'll be able to do in-house," Clough told the committee. "They're talking about a cofferdam of a few hundred feet, dry-pumping everything out and then working along the river. That's something that will be beyond our manpower to do, our people power, and the equipment we have will not be able to handle it."
 
Clough explained that the cofferdam is similar to the work done on the river near the State Road (Route 2) bridge on the west side of North Adams near West Package and Variety Stores.
 
"We don't know the exact numbers yet of an estimate," Clough said. "The initial thought was $600,000 a few months ago. Now, knowing what the plans are, the costs are going to be higher. They did not think there was going to need to be a coffer dam put in [in the original estimate]."
 
The draft capital budget of $592,500 before the Fin Comm includes $500,000 toward the riverbank stabilization project.
 
The town's finance director told the committee he anticipates having about $700,000 in free cash (technically the "unreserved fund balance") to spend in fiscal year 2027 once that number is certified by the Department of Revenue in Boston.
 
View Full Story

More Williamstown Stories