The wooden roof trusses recently installed on the new fire station toppled over sometime late Sunday.

Wind Damage Likely Will Not Delay Williamstown Fire Station Project

By Stephen DravisiBerkshires Staff
Print Story | Email Story

The trusses will be evaluated for repair and reuse but that work is not expected to affect the timeline or cost.  
WILLIAMSTOWN, Mass. — Recent wind damage at the new fire station's construction site will not cost the taxpayers any money and likely will not impact the project's timeline.
 
On Thursday morning, the district's construction consultant said the project's construction manager has a plan to resequence the schedule to make up for the time it needs to reconstruct wooden trusses knocked down by the wind over the weekend.
 
Bruce Decoteau, a retired senior project manager from Williams College, has been advising the Prudential Committee, which oversees the fire district, since the outset of the $22.5 million building project.
 
Decoteau said there are no cameras on site that recorded the damage, but the best guess from construction manager Consigli Construction is that the damage occurred at some time on Sunday evening.
 
According to the National Weather Service, the average wind speed in Bennington, Vt., the closest data point, was 15.1 mph with the highest recorded gust at 46 mph as of 4:43 Sunday afternoon.
 
"I got a photo early Monday morning advising me they had blown over," Decoteau said on Thursday.
 
Decoteau said the damage should have minimal or no impact on the project timeline, which currently has the Fire Department moving into the Main Street station at the end of the calendar year.
 
"What they'll do is pour the second-floor deck prior to installing the rest of the trusses," Decoteau said. "[Consigli] had it sequenced the other way around. This will allow them to keep the trades working and recover most of the time.
 
"You can't have people working underneath the trusses [pouring concrete] while you're setting them."
 
Decoteau said the town's building inspector told the contractor to have a structural engineer check out the steel structure below the trusses to make sure the collapse did not impact any of the metalwork, and the engineer confirmed that there was no effect.
 
"Everything is fine to go, and he sent a letter to Ryan [Contenta] stating accordingly," Decoteau said. "That allows us to get the crane on site and move the trusses to the ground."
 
The wooden trusses will be evaluated to see how much can be repaired and reused and how much needs to be replaced. Decoteau said based on observations from the ground, most of the wood should be usable.
 
As for the cost of repairs from the storm, that expense will be borne by the subcontractor who installed the trusses, Decoteau said.
 
"There will be no financial impact to the Williamstown Fire District or the Williamstown taxpayers," he said.

Tags: fire station,   wind,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Williamstown Housing Trust Gets Update on Summer Street Project

By Stephen DravisiBerkshires Staff
WILLIAMSTOWN, Mass. – Northern Berkshire Habitat for Humanity continues to make progress on a planned four-home subdivision off Summer Street despite rising costs.
 
NBHFH project manager Keith Davis was back before the board of the town's Affordable Housing Trust in August to give an update on the project being developed on a parcel granted to the non-profit by the trustees.
 
"The majority of the site work is now done," Davis said. "The road base is completely in. We won't blacktop the road until the first foundation is done. It doesn't make any sense to drive a loaded cement truck over fresh blacktop.
 
"The detention basin is in. All the [stormwater] structures are in. I talked to [DPW Director] Craig Clough about coming in and looking at it, so he can verify all the structures are in. Because a lot of them get buried. That's the next step, to do that and sod it."
 
The construction package to build the road and stormwater infrastructure cost NBHFH $330,000. The Affordable Housing Trust kicked in $120,000 toward that, and the trustees have committed another $100,000 toward the construction cost of the first home to be built in what the non-profit has named the Meadowlands Subdivision.
 
Davis told the board at its Aug. 19 meeting that a couple of issues have popped up that have slowed the project and added cost.
 
One was the removal of an additional five trees on the 1.75-acre parcel.
 
View Full Story

More Williamstown Stories