Letter: Vote on May 11

Letter to the EditorPrint Story | Email Story

To the Editor:

I am excited to endorse Albert Cummings for Select Board. I have known Albert for decades. I've watched him grow his business from building small additions and renovations to award winning residential and commercial masterpieces. Similarly, I have seen his music career evolve from playing the banjo on Community Auditions, to singing and playing guitar around a campfire, to sharing a stage with some of the greatest blues artists who ever walked the earth. Albert's success in these areas come from a strong work ethic, great people skills, a willingness to always learn new ideas while not casting aside those ideas that are time tested and proven, and the attitude that a job worth doing is worth doing right. These are skills and attributes that will serve our town well.

Albert approaches people, ideas, issues, and opportunities with an open mind. He possesses an uncanny ability to engage with people, put them at ease, and allow them to be heard and has the experience of making tough decisions.

I encourage everyone to vote on May 11.

Jay Merselis
Williamstown, Mass.

 

 


Tags: election 2021,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Williamstown's Cost Rising for Emergency Bank Restoration

By Stephen DravisiBerkshires Staff
WILLIAMSTOWN, Mass. — The cost to stabilize the bank of the Hoosic River near a town landfill continues to rise, and the town is still waiting on the commonwealth's blessing to get to work.
 
Department of Public Works Director Craig Clough was before the Finance Committee on Wednesday to share that, unlike the town hoped, the emergency stabilization work will require bringing in a contractor — and that is before a multimillion dollar project to provide a long-term solution for the site near Williams College's Cole Field.
 
"I literally got the plans last Friday, and it's not something we'll be able to do in-house," Clough told the committee. "They're talking about a cofferdam of a few hundred feet, dry-pumping everything out and then working along the river. That's something that will be beyond our manpower to do, our people power, and the equipment we have will not be able to handle it."
 
Clough explained that the cofferdam is similar to the work done on the river near the State Road (Route 2) bridge on the west side of North Adams near West Package and Variety Stores.
 
"We don't know the exact numbers yet of an estimate," Clough said. "The initial thought was $600,000 a few months ago. Now, knowing what the plans are, the costs are going to be higher. They did not think there was going to need to be a coffer dam put in [in the original estimate]."
 
The draft capital budget of $592,500 before the Fin Comm includes $500,000 toward the riverbank stabilization project.
 
The town's finance director told the committee he anticipates having about $700,000 in free cash (technically the "unreserved fund balance") to spend in fiscal year 2027 once that number is certified by the Department of Revenue in Boston.
 