PITTSFIELD, Mass. — In 2025, the Pittsfield Municipal Airport constructed a new 400-foot taxi lane but by February 2026, one piece was still missing: electricity.
 
Without power connected to the new taxi lane, the airport was unable to begin generating the revenue anticipated from the project, Airport Manager Anita Akor-Yeboah said during a city council meeting in February. 
 
During the recemt Airport Commission meeting, it was announced that the closeout for the design portion of the project was submitted to the agencies on Aug. 21 and hopefully by the end of the week the airport will be sending the closeout for the construction phase portion of that project. 
 
In February, the city approved the appropriation of $445,000 from certified free cash for electrical improvements. According to the meeting minutes, the Federal Aviation Administration and state Department of Transportation the amount will be reimbursed when complete.
 
At the time of the appropriation, the Pittsfield Municipal Airport sent a letter to Mayor Peter Marchetti explaining that the project will include, but is not limited to, removing  existing utility poles and overhead wire, installing electrical handholes, pullboxes, conduits and wire, relocating existing area lights, and pavement patching. 
 
The $445,000 electrical improvement project, which includes a 10 percent contingency over the $403,204 construction bid, is expected to be funded 95 percent by the Federal Aviation Administration, 2.5 percent by MassDOT Aeronautics and 2.5 percent by the city.
 
In August, the FAAA awarded the city with $256,085.26 under the Airport Infrastructure Grants program for Phase 3 electrical improvements to a new 400-foot taxi lane serving a non-exclusive hangar development area at Pittsfield Municipal Airport.

Tags: pittsfield airport,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Neal Tours Berkshire Innovation Center as Pittsfield's Tech Economy Grows

By Sabrina DammsiBerkshires Staff
PITTSFIELD, Mass. —Congressman Richard Neal visited the Berkshire Innovation Center Thursday to highlight $735,000 in federal funding secured for a new cybersecurity training and testing facility.
 
"The number one job of the federal government is to provide for the security of its people. I mean, we should never lose sight of that, whether it's China or Russia, every single day there are these belligerents that are attempting to infiltrate national security here in the United States, and we should not be naive about it," Neal said. "I mean, we can have an argument about proportionality; we can do a lot of different things, but not to miss the point of what they're trying to do every day."  
 
The new cybersecurity facility will provide regional manufacturers and businesses with research and design equipment, specialized lab space, and training facilities and is planned to be housed in a to-be-redeveloped space across the street from the Berkshire Innovation Center (BIC), located at 45 Woodlawn Ave.
 
The derelict property, formerly owned by General Electric, is now known as the William Stanley Business Park.
 
The project is a $7.2 million dollar investment from the state, $5.2 million from the tech collaborative, $2 million from bond funding secured by Neal, and $1 million that will be split into two phases: $500,000 for BIC to begin building and $500,000 for Myrias Optics to start production in Pittsfield, said Mayor Peter Marchetti. 
 
BIC Executive Director Ben Sosne said manufacturers often highlight the need for help with cybersecurity, particularly in meeting the security requirements necessary to conduct business with General Dynamics and other major contractors.
 
Collaborators in the field and the public sector have recognized the need that has only grown since technology has advanced and is a great career opportunity, Sosne said. 