image description
Conservation Commissioners get a tour of the dredging being done to remove sediment ahead of the Bel Air Dam's removal.
image description
Flooding behind 200-year-old dam concerned the Conservation Commission.
image description
Sediment is being transported off-site to Seneca landfill in New York. The majority of the sediment has been removed, according to construction updates, and should be completed by mid-May.
image description
A cut was made in the dam and pumps installed to lower the water level in the dam's impoundment.
image description
Commissioner get an update on the progress and efforts to reduce flooding.

Flooding Leads Pittsfield ConCom to Bel Air Dam Deconstruction Site

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — The Bel Air Dam project team toured the site on Monday with the Conservation Commission to review conditions following a flooding incident

Work has been on hold for two weeks after melting snow and a release of water from Pontoosuc Lake led to water overtopping of the almost 200-year-old, abandoned dam. The project team says deconstruction is still on track to end in December. 

"They have plenty of time to finish the work, so they don't expect that they're going to need extra time, but we're all waiting," reported Robert Lowell, the Department of Conservation and Recreation's deputy chief engineer. 

"… it's unfortunate, but the high-water conditions in the spring, we did have in the contract that the site might flood, so there was supposed to be a contingency for it, and we're now dealing with the complications of that." 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade. 

The dam on Pontoosuc Brook dates to 1832 and was used for nearly a hundred years to power a long-gone woolen mill. It's being targeted for removal, using American Rescue Plan Act funds, because the stacked stone structure poses a significant danger to homes and businesses downstream. Excavation of sediment began last fall by contractor SumCo Eco-Contracting of Wakefield. 

Earlier this month, community members noticed flooding at the site bordering Wahconah Street; water levels were down by the next week. Conservation commissioners called for the site visit with concerns about the effects of the water release and how it is being remedied.  

The group got a look at the large project area near the dam and asked questions. Chair James Conant explained that community members wanted to know the cause of the flooding. 

Jane Winn, former executive director of the Berkshire Environmental Action Team, said this was specifically brought up at the Conservation Commission hearing to ensure this sort of thing didn't happen. 

"I just wanted it on record that this is twice in a row for SumCo in Pittsfield, and I find that unacceptable," she said about the environmental restoration and construction company. 



Contractors put a cut in the water flow for a controlled release and installed two turbidity curtains downstream of the dam. Two 24-inch pipe pumps on site can be used if needed. 

Pontoosuc Lake's water level management is not handled by Pittsfield, and an inquiry has been made about the lake's levels. The lake's spillway is operated by the state Department of Conservation and Recreation, which did some "response actions" to the rising water levels from snowmelt around the weekend of March 11. 

Lowell said, "We could have been better prepared for it." 

Jennifer Doyle-Breen, of AECOM*, which developed the ecological restoration proposal, added that despite the release, the water level at Pontoosuc has remained "pretty high." 


"When I was recently up at the dam, the water was flowing over the top of the dam. There's nothing DCR can do about that once the water gets up that high," she said. 

"There was a lot of snow, and we had a couple of really warm days. I do think that contributed to the situation here." 
 

*Architecture, Engineering, Construction, Operations, and Management
 


 


Tags: conservation commission,   dam removal,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Companion Corner: Princess at Berkshire Humane Society

By Breanna SteeleiBerkshires Staff

PITTSFIELD, Mass. — There is an energetic girl waiting to find her new home at the Berkshire Humane Society.

iBerkshire's Companion Corner is a weekly series spotlighting an animal in our local shelters that is ready to find a home.  

Princess is a six year old shepherd mix that has been at the shelter for just over a month.

Canine caregiver and adoption counselor Simone Olivieri told us about Princess.

"She's very social, very friendly. When you're out walking her, she just wants to go say hi to every single new person. Loves to make new friends. She's a lot of fun. She's very active. She's very spunky. She's very playful, and she's going to need a very very active family who's going to do a lot with her." 

But Princess is no stranger to the shelter. She was a puppy five years ago and got adopted quickly, but now she needs a new family to take care of her.

"She was adopted out fairly quickly as a young puppy. She's been in the same home for the past five years. Unfortunately, they were moving out of state somewhere," Olivieri said. "They could not take her with them, so she ended up coming as a return to shelter, and she came back to stay with us."

Princess needs to go to a home as the only animal or with other male dogs that are her size or bigger.

"Her perfect home would be kids eight and up. No cats. No small animals. She has quite a prey drive. She could go to a home with another dog around her size or larger, preferably a male dog. She does a little bit better with male dogs, and she's looking for a home where people are home quite a bit, so that she's not left alone for too long. She has some separation anxiety," Olivieri said. 

She also needs a very active home that can let her use her energy every day, as she is very rambunctious. Especially with playing with her favorite toy, the flirt pole.

"She could use a home where people are going to give her a lot of attention and more than just a few walks a day; she's going to need lots of exercise, lots of playtime, lots of mental stimulation," Olivieri said. "She likes to learn, so someone who would be willing to take her to training classes or work on some training with her, as well as hikes, getting out and about, doing new things, different things. She is very athletic. She'd excel at things like agility, some dog sports. Just someone who is really going to want to engage and do a lot of different kinds of activities with her." 

Once you let her get her energy out, she is a cuddler who wouldn't mind being held like a baby from time to time.

"She's very sweet. She's very cuddly. She's very affectionate, but she is not a couch potato. She will stay on that couch with you for a little bit, and then she's ready to go off and do something else. So she's very busy. She's very active," Olivieri said. "Once all of her exercise needs are met during the day, she will settle down nicely, and she will want to be right by your side, cuddle with you at night on the couch, sleep with you."

Princess is very healthy but does experience some anxiety and is not fully potty trained and might have the occasional accident.

"She does have a little bit of anxiety, so she is on some medication for it right now," Olivieri said. "So a lot of structure, a lot of outlets, and familiarity, getting used to a new routine and everything is gonna be really good for her. I mean, she's just lovely. Like I said, she's very social. She likes to play with other dogs. She likes to meet new people."

View Full Story

More Pittsfield Stories