DALTON, Mass. — The town's lowest-rated bridge is slated for an approximately $2.5 million reconstruction project.
During the Select Board meeting on Monday it was announced that the town has been awarded a $1 million grant through the Municipal Small Bridge Program for the bridge on Grange Hall Road over Barton Brook, located near Patricia Avenue.
The town's engineers estimated the total cost to complete is $2,335,000, however these estimates tend to run a little high, Town Manager Eric Anderson said.
"It's an expensive project, there is no question but it does have to be done. That is the culvert the town has with the lowest rating in town," he said.
If the town were to decide to delay the project, which would revoke its eligibility for the state grant, then it would be on the hook for the total cost.
When the town agrees to the grant, it is agreeing to this bridge project, Anderson said.
According to the state website, the short span bridge, built in 1938, was inspected on July 20, 2025 and rated as structurally deficient.
It was said that the town will need to allocate the remaining approximate 1,335,000 but this is the cheapest it will ever be because of the state grant.
The town can allocate this funding through a combination of free cash and capital stabilization without having to go into short-term debt. This would need to be approved at a special town meeting, likely in September or October. The town has $1.49 million in Capital Stabilization.
According to project documentation, the anticipated timeline calls for the project to go out to bid in fall 2026, with a contractor expected to be selected during the winter of 2026-27 and construction beginning in spring 2027.
This grant award is reimbursement-based, similar to the Chapter 90 Program. Grant recipients may submit reimbursement requests as costs are incurred.
"The replacement scheme for this project will be to take it from a twin pipe steel corrugated steel culvert to an actual box culvert with an open bottom," Anderson said.
For practical purposes, it will be a prefabricated bridge, he said, meaning it is manufactured in a factory then shipped in pieces or modules to the construction site for final assembly.
The entire existing structure will be demolished during the project. According to documentation on the project, no existing drawings of the bridge are known to exist.
However, based on portions of the structure observed, it consists of two 5-foot-diameter steel pipes approximately 70 feet long, positioned at a 45-degree angle beneath Grange Hall Road, project documentation says.
It has masonry headwalls at both ends, supports a 21-foot-wide roadway with two travel lanes, and has W-beam guardrails on both sides.
The project will consist of installing temporary traffic controls, erosion and sediment control, a temporary utility structure, and control of water, the document said.
Once demolished a substructure will be installed and protective riprap covered with 12 inches of natural streambed material will be placed, it said.
Then there will be the installation of bridge units, construction of wingwalls, and modified third beam. Additionally existing utilities will be relocated, the document said.
There will be a full-depth reconstruction along the approach roadway, installation of guardrail and other incidental work necessary to complete the proposed project, it said.
This project will qualify the town for the federal local bridge program when it needs to be replaced or repaired a century from now, which will be cheaper, Anderson said.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Pittsfield's Christian Center Rebrands as 'The Center'
By Brittany PolitoiBerkshires Staff
PITTSFIELD, Mass.— The Christian Center is becoming The Center, and assures the community that while the logo and name have changed, "Our heart has not."
The rebrand was announced on Tuesday after months of listening sessions, community conversations, and surveys. It was emphasized that the organization's heart, mission, and commitment to the community are unchanged.
The Center will host its annual Community Day, including a name change celebration, on Aug. 22 from 11 a.m. to 2 p.m.
"While our name is shifting, our core purpose remains steadfast. Alongside our new name, we are introducing our defining tagline—Nourish. Empower. Connect.—which reflects the three principles guiding everything we do," Executive Director Jessica Jones wrote in a newsletter.
"Whether through our food pantry, meal program, free clothing boutique, or community events, our work remains focused on helping our neighbors access essential resources, build connections, and thrive."
The new logo features a fork, carrot, heart, and shirt, representing the pillars of The Center's service.
The Christian Center was incorporated in 1974, but it dates back to the early 1890s, when it was the Epworth Mission, founded by the Methodist Church.
Today, its main focus is food insecurity, but it also provides clothing, household items, and sanitary supplies to those who need them. The Center operates a food pantry, upstairs free shop, and serves breakfast and lunch, as well as offering assistance in accessing resources.
The community was invited to come to the village for free and take part in a wide range of activities including tours, live music from Ida Mae Specker Trio and Tanglewood, demonstrations, and more. click for more