Flushing of the City of Pittsfield's Water System: April 27-May 1

Print Story | Email Story
PITTSFIELD, Mass. — Monday, April 27 marks the start of phase two for the spring flushing schedule of the City of Pittsfield's water system, as phase 1 is now complete. 
 
Water mains throughout the city will be flushed through hydrants over the next several weeks to remove accumulations of pipeline corrosion products. Mains will be flushed Monday through Friday each week, except holidays, between the hours of 7:30 a.m. and 3 p.m. This phase of flushing is expected to occur between April 27 to May 1.
 
Flushing is expected to affect the following areas:
  • Starting at Unkamet Park Drive heading west up to North Street working north to the Broadway and Lakeview streets neighborhood.
  • Starting at Plastics Avenue moving west on Dalton Avenue including the Allendale and Allengate neighborhoods. Then moving west onto Tyler Street into the Morningside neighborhood, including Springside Avenue, pushing west to North Street.
  • Lincoln and Fenn streets, Silver Lake, Wendell Avenue and the surrounding vicinity, pushing west to North Street.
  • South Mountain and Tamarack roads, Dan Fox Drive, and south to the Pittsfield-Lenox line.
Although flushing may cause localized discolored water and reduced service pressure conditions in and around the immediate area of flushing, appropriate measures will be taken to ensure that proper levels of treatment and disinfections are maintained in the system at all times. If residents experience discolored water, they should let the water run for a short period to clear it prior to use.
 
If discolored water or low-pressure conditions persist, please contact the Water Department at (413) 499-9339.
 
 
If you would like to contribute information on this article, contact us at info@iberkshires.com.

BCC Sees Another $1M for New Trades Program

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — Berkshire Community College was allocated more than $1 million from the state for an HVAC and heat pump trades program.

This will help BCC renovate an existing space into a lab and classroom, with the hope of welcoming the program’s first students in early 2027. Executive Director of Workforce and Community Education Linda Clairmont said there is "clearly" an interest, a lot of momentum, and demand for the skilled trades.

"We are beyond excited about this opportunity, not only for the college, but for the region, to be able to create a skilled trades program for adults, and it's a complement to what is already happening at the college," she said. 

The $1,188,635 award was announced on Tuesday as part of $13.4 million to 13 state community colleges through the Mass Clean Energy Center’s new Heat Pump and HVAC Training Network.  Between state and federal funding, the college has recently been allocated more than $2 million to diversify its educational offerings. 

Earlier this month, U.S. Rep. Richard Neal visited the college to highlight the $995,000 he secured through congressionally directed spending for a Trades Academy

The nearly $1.2 million in state funds will support a renovation on the first floor of the field administration building for an HVAC heat pump and lab classroom, along with two cohorts of ten students. 

"We have made a lot of progress," Clairmont reported. 

"We've identified a location, right on campus. We are working with architects and engineers right now to design the space, along with some expertise in what is state-of-the-art for HVAC training in real-world environments." 

View Full Story