PITTSFIELD, Mass. — The city is seeking a total of $28 million in borrowing authorizations to upgrade its drinking and wastewater infrastructure. 

This includes $13 million for upgrades to the wastewater treatment plant and $15 million for upgrades to the Cleveland and Ashley Water Treatment Plants, which are located outside Pittsfield. The City Council referred the $15 million borrowing request to the Finance Subcommittee on Tuesday. 

The full drinking water project is expected to cost $165 million over the next 8 years, with $150 million for long-term construction and $15 million for near-term needs. The initial ask would fund the final design and permitting for Phases 1-3, Phase 1 of interim updates, allowances, and contingency. 

After the meeting, Commissioner of Public Services and Utilities Ricardo Morales explained that these are needed repairs so the current infrastructure can be stretched a little longer while design work is underway.

Pittsfield's two Krofta drinking water treatment plants were installed in the 1980s. The city says they are beyond anticipated useful service and at risk for catastrophic failure that could leave Pittsfield with a shortage of potable water. 

Krofta is a compact filtration system that Pittsfield will continue to use. There are four units at the Cleveland WTP and two at the Ashley WTP.  Morales said the system is "very good" but needs to be upgraded. 

"We were one of the first to use that type of technology in the 80s, and it's outdated now, and getting parts and getting repairs to it is very costly because of the outdated technology that it's using, and we can replace that with better infrastructure," he explained. 

"We need to build a chemical facility on the Cleveland side. We already have that done at Ashley with [American Rescue Plan Act] funds, largely, and then we need to build better tank holding systems at the plants to allow for chlorination to happen at the plant, instead of on its way down to Pittsfield." 

The Ashley WTP received more than $4 million in ARPA funds. 


From 2019 to 2022, the city piloted a new generation Krofta with approval from the Department of Environmental Protection.  Morales said they need to be tested on-site to ensure that they can provide the expected quality of water. 

According to the project timeline, starting this year, two finished water storage tanks would be designed and constructed, chemical improvements would be made at the Cleveland WTP, and the East New Lenox Road flow control station would receive a new pump station to allow the Ashley WTP to be offline during the third phase. 

Both WTPs would undergo "major" process and building improvements starting in 2028, and there would be upgrades to the Lower Ashley Reservoir and gatehouse.  Construction is expected to be complete in late 2033.

Pittsfield provides drinking water for Dalton, the town pays for sewer, and the city has been in conversations with the Dalton Fire District about the upgrades, Morales reported. 

Dalton anticipates a rise in water and sewer rates. Town Manager Eric Anderson recently said Pittsfield has proposed raising its fees for the town to include a charge to contribute towards the capital costs, but there is no official agreement with the city yet. 

Last week, the Finance Subcommittee discussed the borrowing for sewer infrastructure, which was reduced from $15.2 million.  After a couple of hours of questions and concerns, it was tabled until next month. 

Councilor at Large Kathy Amuso referenced the conversation on Tuesday, asking for a "lot of data" at the next Finance Committee meeting. 

Funding would support a new administration and laboratory building at the plant. The WWTP’s existing laboratory building was built in 1938 and adapted for use in 1973, and is said to no longer meet current needs. 

Mold, layout issues, rodents, ineffective air conditioning, and insufficient lab space were cited as conditions that necessitate the project. This means samples have to be sent to external labs, causing delays, while the new lab will allow same-day analysis. 


Tags: drinking water,   treatment plant,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Hinsdale OKs Police Department Audit After Fatal Shooting

By Brittany PolitoiBerkshires Staff

HINSDALE, Mass. — The town has approved $25,000 for an administrative review of the police department, more than two months after police fatally shot 27-year-old Biagio Kauvil during a mental health crisis. 

Town Administrator Robert Graves said the shooting on Jan. 7 is not the only focus of the audit, and it will be several months before the Select Board receives a final report. 

During a special town meeting on March 11, an article appropriating $25,000 from free cash for an independent consultant to conduct a professional evaluation and audit of the Town's Police Department was approved. The audit includes a review of the department's policies, protocols, operations, and procedures, and concludes with a written report. 

"The Berkshire County District Attorney's Office and Massachusetts State Police are investigating the shooting, and we await their conclusions.  As we look to move forward, the International Association of Chiefs of Police, our insurance company (MIIA/Cabot Risk), and our legal counsel have recommended that the town hire an independent law enforcement consultant or firm to conduct a comprehensive administrative review of our police operation," Graves wrote in an email to iBerkshires on Friday. 

"This event is not their focus; they will assess the overall operation. We want a written assessment of our police operation's strengths and weaknesses to help Hinsdale make future changes and improvements." 

He said after completing the procurement process and signing a contract with a reputable consultant or business, it will most likely be several months before the Select Board receives the final report. 

"Still, it will help the town and police department move forward," Graves wrote. 

Last weekend, family and friends of Kauvil stood in Park Square asking for justice. A flier for the standout reads "Biagio was killed by police while experiencing a mental health crisis. Now, over seven weeks later, authorities have not yet provided any updates.

View Full Story

More Pittsfield Stories