NORTH ADAMS, Mass. — Officials expect to have bids on the $65 million Greylock School project in hand by the end of January. 
 
The bidding documents were complete as of Tuesday and were expected to be available on Project Dog, an online document platform for contractors, before the end of the week. 
 
"If they're interested, they can download the documents to review," Timothy Alix of Collier's International, the owner's project manager, told the School Building Committee on Tuesday. "Only pre-qualified bidders will be allowed to bid at this point. And our two bid dates, we have two separate ones, one for the filed subbidders, and that's going to be Dec. 17, and then with the (general contractors) being due on Jan. 14. ...
 
"By mid-January, we'll have our our number from a general contractor." 
 
The committee does have the option to extend the deadline for any additional plans or clarifications. The documents will have two alternates — the pickleball/basketball court and the Appalachian Trail kiosk. 
 
Jesse Saylor of TSKP Studio, the project designer, clarified that the kiosk was always part of the plans but is considered an alternate for pricing. The court has an estimate of $300,000; the project has so far been running $1 million below the estimated cost. 
 
He did give committee members a bit of scare when he quoted a price of $500,000 for the small kiosk, which will have water and electricity during the summer for hikers. 
 
"Maybe I'm missing something here, but it's a kiosk," said member Richard Alcombright."It would seem to me that there's water in the road, and it also seems to me that the power is close by. No matter where you go, you're gonna have lights in the parking lot."
 
Mayor Jennifer Macksey asked if had an extra zero and Saylor said, "I think it's expanded in its cost and scope since our last estimate," but agreed the price was "overkill" and he would check back on the actual estimates.
 
The trail kiosk was put in on school property on Phelps Avenue, over which the Appalachian Trail runs, and North Adams was designated as an Appalachian Trail Community in 2016. The kiosk is dedicated to Thomas "Moto" Sheehan, a city native and avid hiker who died young. 
 
"We made pretty much significant verbal commitments to that piece of the property, and the community went through a lot of time and a lot of work to get our designation for the AT," said Alcombright, mayor when the city received the designation. "I certainly think we should have a basketball court, pickleball. I think it should be a nice center for the community. But I just want to make a strong statement that that kiosk, in some way, shape or form has to remain. That's just my own opinion, and I'm sticking with it."
 
The mayor confirmed it will "remain in some form or fashion, but not at $500,000."
 
Member David Moresi joked you could build a five-bedroom house for that price and that it was incumbent upon the committee to keep a sharp eye on costs and look outside the project for funding, if needed. 
 
"If the need comes, there's going to be the community rallying behind it," he said. "There's a very symbolic nature behind this kiosk, as well as the hikers of the AT that it serves. So do keep that in mind."
 
Saylor said he would also have to check with the Conservation Commission about the pickleball court, since it wasn't clear if that alternate had been part of the plans approved last month. He believed it would be far enough in setback from the wetlands to not be significant. 
 
The committee held off on setting its January meeting, considering it might combine with February so as to have time to review the January bids. Alix said only three general contractors have been prequalified.
 
"Once we check their documents, their payment and performance bonds, and check their goal — how they plan to achieve their goals for supplier diversity — and their insurance certificates and that sort of stuff that won't take long once they get them to us," said Alix. "So I think that first or second week in February would work as fine as well."

Tags: Greylock School Project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

McCann Committee Gets First Look at $17M Renovation Progress

By Jack GuerinoiBerkshires Staff

The project is in the home stretch with roofing and some windows and doors still to be installed. Superintendent James Brosnan also pointed above to HVAC improvements in the Guidance Office. 

NORTH ADAMS, Mass. — The McCann School Committee got a first look at the final stretch of a $17 million overhaul aimed at making the 64-year-old vocational school safer, quieter and more energy-efficient.

After a brief School Committee meeting Thursday, Superintendent James Brosnan led the members through the school, highlighting some of the changes made in the 64-year-old building.

"Just seeing this gives you a magnitude of the amount of work that goes on," he said.

The upgrades are being funded through the Massachusetts School Building Authority's Accelerated Repair Program and the Northern Berkshire Vocational School District's member towns.

Work was supposed to be completed before the start of the school year, but weather and the removal of materials caused a delay.

The tour was all indoors, and Brosnan told a disappointed committee that he was hesitant to take them onto the roof at night, but said the new roof is near 80 percent down.

"We have another 10, and 10 percent of that missing 20 is in the AVB [air and vapor barrier] and removal phase," Brosnan said. "That particular area is across the front, down the post-secondary ... we are going to pick up from guidance. So we have that plan going through next week. Fingers crossed, within two weeks we will have that piece down."

He said the roof has been built up and insulated for more efficiency.