Public Meeting on the Kirvin Memorial Park ecological Improvements

Print Story | Email Story
PITTSFIELD, Mass. — The City of Pittsfield, Housatonic River Natural Resources Trustees, and General Electric Co. will be hosting a public meeting on Wednesday, June 11 at 6:00p.m.
 
This meeting will take place at Herberg Middle School located at 501 Pomeroy Avenue in the auditorium.
 
At this meeting, the presenters will review the significant floodplain and habitat restoration and enhancement plan for Kirvin Memorial Park. A team of specialists will be working to improve the conditions of approximately 17 acres in the flood plain of Sackett and Ashley Brooks in the south end of Kirvin Memorial Park by removing invasive plant species and establishing native vegetation.
 
In addition, there are plans to expand wetland conditions in a portion of the floodplain area. These invasive plants collectively impair the overall habitat diversity and functions of the ecosystem.
 
The public is encouraged to attend to listen to the presentation and provide feedback on the proposal.
 
This project is slated to start in the fall of 2025. During this project, the park will remain open to the public.
If you would like to contribute information on this article, contact us at info@iberkshires.com.

Dalton Planning Board Denies Berkshire Concrete's Special Permit

By Sabrina DammsiBerkshires Staff
DALTON, Mass. — After five meetings, the Planning Board voted to deny Berkshire Concrete's special permit, however, the company can still reapply before its current permit expires. 
 
After about 40 minutes of deliberation, board members reiterated recurring concerns raised in previous meetings: the company's lack of clear mitigation plans and ambiguous documentation outlining its work plans.
 
"I really have no confidence in their proposal so far," said Chair Zack McCain III.
 
The board denied the permit without prejudice, meaning Berkshire Concrete, a subsidiary of Petricca Industries, can reapply before its current permit expires in December 2027. 
 
According to the current permit, earth removal, such as excavation, processing, and reclamation is allowed on lots 217-3 and 106-55.1, but is subject to several conditions set forth in 1992, 1994, and 2000. 
 
Conditions include hours of operations, traffic regulations, restoration requirements, and other stipulations. 
 
This decision indicates the board's belief, based on testimony and provided evidence that the excavation activities in the areas cannot occur without having a negative impact on the abutting neighborhood. 
 
View Full Story