The Peck's Road Bridge is clear and open for the first time in a year.

Pittsfield's Pecks Road Bridge Opens

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

The old bridge was demolished last  year and the new one completed within six months. The span had been limited to one lane for five years. 

PITTSFIELD, Mass. — After nearly a year of full closure, the Peck's Road bridge is back online.

On Tuesday, the city announced on social media that the $1,689,000 project was complete. The bridge was reduced to one lane of traffic for five years and completely closed last summer after an inspection from the Massachusetts Department of Transportation found six areas of deterioration.

This means that drivers will no longer need to detour from Peck's Road to Onota Street, Vin Herbert Boulevard, and to Valentine Road. There will be no ribbon cutting, according to the city. 

Because it had to be fully shut down, construction took about half the time it would have with a partial closure, which was initially planned.

The bridge was first ordered to be closed completely in the fall of 2019. 

"The state made the requirement after they performed the annual inspection. After hearing that the bridge needed to be closed we requested a second review of the inspection and state came back, allowing the bridge to be open for a one lane 10 feet wide," Commissioner of Public Services and Utilities Ricardo Morales wrote VIA email, adding that the state of the bridge and prior inspections didn’t find that it needed to be replaced.



Design started after the one lane closure but was "quickly" delayed by the COVID-19 pandemic in 2020 and 2021. The state approved the bridge design in spring 2024.

Morales explained that the project was put out to bid, but before the work began, the state's annual inspection determined that the whole span had to be closed down. At that point, the city had to revisit the design and construction plan since it had been assuming that it would be a phased build that maintains one lane of traffic.

"While this represented initial delays and setbacks early in the project construction phase, it resulted in a faster construction since building the bridge one side at a time while maintaining one lane access would have taken a full year's worth of construction instead of six months' actual construction," he wrote.

Work included demolishing the old bridge, which happened last fall, and the reconstruction of the span over Onota Brook. A paved sidewalk runs along one side of the bridge.

The bid was awarded to Rifenburg Construction of Troy, N.Y.

During the inspection in July 2024, MassDOT found:

  • settlement in the wearing surface along the east curb, full length by 3 feet wide by up to 2-inches deep (This aligns with bay 17)
  • buckling of beam 18 along with a gap between the deck and the beam forming up to 1/4 inch
  • beam 17 bottom flange is distorted up to 1/4 inch full length
  • beam 16 bottom flange is distorted 3/4 inch full length. (Beam has several holes in the flange and web)
  • beam 14 has holes at the north end and the web is distorted 1 1/4 inch out of the plane
  • beam 13 web is distorted 5/8 inch out of the plane

Tags: bridge work,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield Council Revisiting DEI Office Rename

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The conversation about the DEI office renaming that was halted by a charter objection will resume on Tuesday. 

The City Council will discuss a request from Mayor Peter Marchetti to rename the Office of Diversity, Equity, and Inclusion.  

It proposes to rename the DEI office to the Office of Equity, Access, and Opportunity and merge the Human Rights Commission and Affirmative Action Committee into an Equity, Access and Opportunity Commission.

The Ordinance and Rules Subcommittee supported the changes in August, and in September, Ward 2 Councilor Cameron Cunningham delayed the vote with a charter objection. 

Pittsfield's City Code prohibits charter states that "if a single member present objects to the taking of the vote, the vote shall be postponed until the next meeting of the city council." It also stipulates that at least four members must object if it is an emergency measure.

Cunningham also submitted a petition, which was referred to O&R under Rule 27, to replace the DEI Office and the Human Rights Commission with an equity, access, and opportunity coordinator in the Department of Community Development, with formal complaints and Equal Employment Opportunity and Affirmative Action functions assigned to Human Resources.

At the last meeting, he spent more than an hour querying the mayor and chief diversity officer about functions and effectiveness of the department, wanting more quantitative data.  Cunningham proposed an ordinance that he says keeps Pittsfield's commitment to equity, access, and opportunity, "refocuses it on measurable results for our residents, and delivers it at a fraction of the current cost." 

Under this petition, the equity, access, and opportunity coordinator would be a $60,000 to $80,000 per year position.

The DEI Office's fiscal year 2027 budget was about $200,000 after cuts during budget season; $106,700 for the chief diversity officer and $58,000 for the administrative assistant. The coordinator would be appointed by the director of community development and the mayor. 

View Full Story

More Pittsfield Stories