Orchard Road has suffered from flooding for years because of poor drainage. A new drainage system will replace the piping and catch basins and the road will be repaved.
Dalton's Orchard Road Reconstruction Pushed to 2025
DALTON, Mass. — The reconstruction of Orchard Road is now projected to take place next year.
The last estimate for construction was overly optimistic because, at the time, it was unclear how long obtaining the two easements would take, Town Manager Thomas Hutcheson said.
Louise Frankenberg, the owner of one of the easements on Orchard Road, donated the 3,979 square-foot piece of land to the town.
The other easement on North Street, owned by Amy Musante, is a more substantial chunk of land, 14,364 square feet, and was purchased for $7,000.
Voters approved allocating this amount from free cash during the annual town meeting in May.
Now that the town has received the easement plans, it has to file with the Registry of Deeds and pay Musante.
Once that is complete, the town can go out to bid. However, because it is already well into construction season, construction companies are likely already fully booked.
"If we go out to bid now for the next construction season, though, we’ll be much more likely to get competitive bids," Hutcheson said.
The road, which is often used as a connector to Route 9, has had flooding for many years because of undersized drainage pipes, Highway Superintendent Edward "Bud" Hall has previously said.
Most of the flooding is in the middle of the road and into abutting residents' yards, sometimes reaching a depth of 6 inches near the Pease Avenue and Appletree Lane intersections to the East Branch of the Housatonic River.
The reconstruction includes a new drainage system that will replace the piping and catch basins with new and bigger pipes and move them to the center of the road from Pease Avenue to the bridge.
The blacktop on the other side of the road, near Wahconah Country Club and from the Massachusetts Public Works building to Route 9, will be replaced.
This project has been six years in the making and is now possible thanks to the town's approval for a state MassWorks grant of $1 million. The grant will be used to address the street's drainage issues. More information on the grant is here.
This was the second time the town had applied for the grant and after getting some feedback on from the state on the first submission.
The contract with the state was executed in January 2024 and expires on June 30, 2025, at the end of the fiscal year. The state Department of Transportation spokesperson confirmed that the contract has been extended until June 30, 2027, and it would not be considered delayed until after that date has passed.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Hinsdale OKs Police Department Audit After Fatal Shooting
By Brittany PolitoiBerkshires Staff
HINSDALE, Mass. — The town has approved $25,000 for an administrative review of the police department, more than two months after police fatally shot 27-year-old Biagio Kauvil during a mental health crisis.
Town Administrator Robert Graves said the shooting on Jan. 7 is not the only focus of the audit, and it will be several months before the Select Board receives a final report.
During a special town meeting on March 11, an article appropriating $25,000 from free cash for an independent consultant to conduct a professional evaluation and audit of the Town's Police Department was approved. The audit includes a review of the department's policies, protocols, operations, and procedures, and concludes with a written report.
"The Berkshire County District Attorney's Office and Massachusetts State Police are investigating the shooting, and we await their conclusions. As we look to move forward, the International Association of Chiefs of Police, our insurance company (MIIA/Cabot Risk), and our legal counsel have recommended that the town hire an independent law enforcement consultant or firm to conduct a comprehensive administrative review of our police operation," Graves wrote in an email to iBerkshires on Friday.
"This event is not their focus; they will assess the overall operation. We want a written assessment of our police operation's strengths and weaknesses to help Hinsdale make future changes and improvements."
He said after completing the procurement process and signing a contract with a reputable consultant or business, it will most likely be several months before the Select Board receives the final report.
"Still, it will help the town and police department move forward," Graves wrote.
Last weekend, family and friends of Kauvil stood in Park Square asking for justice. A flier for the standout reads "Biagio was killed by police while experiencing a mental health crisis. Now, over seven weeks later, authorities have not yet provided any updates.
Qwanell Bradley scored 33 points, and Adan Wicks added 29 as the Hoosac Valley boys basketball team won a Division 5 State Championship on Sunday. click for more
Our Friday Front Porch is a weekly feature spotlighting attractive homes for sale in Berkshire County. This week, we are showcasing 140 Hancock Road.
click for more
Pittsfield's new ice rink had a short season because of unpredictable weather, and the city is soliciting memories about the Wahconah Park grandstand before it is demolished. click for more
Morales reported that the city will take a step back and revisit the basis of WWTP design, and return with a refined proposal that addresses concerns.
click for more